ADNOC Borouge Innovation Centre

Al Rayyan Stadium

Qatar

Back

The gateway to the desert opens its doors to the world

Project Description

The project comprises of the construction of Al Rayyan Stadium in the place of former Ahmed bin Ali Stadium in Al Rayyan, western suburb of Doha. Its capacity is set at 40,000.

The concept combines a simple, nearly rectangular bowl with exciting outer cladding which adds dynamism to the building. Utilizing traditional Arabic patterns, the outer webbing allows sunlight access to the infrastructure within the stadium. Sun will also play important role in sustainable use of the stadium thanks to photovoltaic panels.

Scope

CML are employed by Al Balagh Larsen and tobro JV to provide full Commissioning Management for Mechanical, Electrical, ELV, Public Health and Specialist Services.

Project Start and Completion Dates:

Main Works Construction Start - Q2 2016

Overall Project Site Completion - Q3 2019