Bahrain Oncology Centre

The Hilton Family Hotel,Yas Island

Abu Dhabi

Back

Modern quarters in a high-end hotel with an outdoor pool & a spa, plus multiple dining options.

Project Description

The project comprises the construction of a family hotel and resort on Yas Island in Abu Dhabi for the developer Miral Asset Management and operator Hilton Hotels. The development consists of the following; 1 Basement and 12 Floors and 2 Floors of Retail. The total GFA including Hotel, Retail and Cark Park is approximately 220,000m2

Scope

CML are employed by the Main Contractor, Sanjose Fibrex JV to carry out the Commissioning Management of all the Mechanical, Electrical, ELV, Public Health and Specialist Engineering Services

Project Start and Completion Dates:

Main Works Construction Start - Q3 2017

Overall Project Site Completion - Q3 2020